Reconciled operational metrics, workcenter capacity signals, and constraint-aware decision support.
Live cross-module operational exceptions requiring human decision and confirmation.
304 SS Sheet 0.25in: Need 8 sheets by Aug 30 to meet delivery date.
Recommended: Transmit expedited purchase order to Ryerson ($420/sheet, 3d lead time).
Tradeoff: $150 freight fee avoids 48h shopfloor press brake idle time.
CNC Press Brake Cell scheduled for 83.4 hours vs 80.0 available hours this week.
Recommended: Authorize split setup on secondary 150-ton brake (EQ-BRAKE-01).
Tradeoff: Adds 45min setup changeover but restores on-time buffer.
94.5%
Target: >= 95.0%99.2%
Target: >= 98.0%97.4%
Target: >= 95.0%98.7%
Target: >= 98.0%72.4%
Target: >= 65.0%98.7%
Target: >= 95.0%Measured machine and station hours committed for current week.
62.5 / 80.0 hrs committed
83.4 / 80.0 hrs committed
94.0 / 120.0 hrs committed
72.0 / 80.0 hrs committed